Project profit calculator
Find out whether a job is on course to make money, and how many hours are left before it stops. Nothing you type leaves your browser.
This is an estimate from the numbers you enter. It assumes the rest of the job goes at the same pace as the work so far.
How the numbers are worked out
Fintoras is being built to keep this sum up to date for every project, from the hours and costs your team already records.
Projected hours
Hours logged so far, divided by the share of the work that is done. 260 hours at 50% complete projects to 520.
Projected cost
Projected hours times your cost per hour, plus other costs.
Margin
Fee minus projected cost, as a share of the fee.
Break-even
Fee minus other costs, divided by cost per hour. Past this many hours, the project loses money.
Slack
Break-even hours minus projected hours. It is what is left over if the rest of the job goes at the same pace.